Change of Land Use
CONTACT PERSONS FOR
CHANGE OF LAND USE IN KASHMIR DIVISION

Change of Land Use (CLU) in Kashmir/Jammu & Kashmir, particularly conversion of agricultural land to non-agricultural use such as commercial, industrial, hotel, cold storage, warehouse, etc., the application is generally dealt with under Section 133-A of the J&K Land Revenue Act, 1996 and the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022. The competent authority is the District Collector (Deputy Commissioner).
Below is a practical, Kashmir-specific CLU file checklist, NOC checklist and ready-to-use application format for conversion of agricultural land to non-agricultural use.
The current framework is the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022, issued under the J&K Land Revenue Act. The District Collector/DC is the competent authority, and applications are processed through the district-level mechanism. The regulations provide for online filing and ordinarily contemplate disposal within 30 days once the application is complete.
1. MASTER CLU DOCUMENT CHECKLIST — KASHMIR
A. Application & Applicant Documents
| S. No. | Document | Required |
|---|---|---|
| 1 | Prescribed CLU Application Form | ✓ |
| 2 | Applicant’s full name | ✓ |
| 3 | Parentage / constitution of applicant | ✓ |
| 4 | Permanent & correspondence address | ✓ |
| 5 | Aadhaar / valid identity proof | ✓ |
| 6 | PAN Card | ✓ |
| 7 | Mobile No. & E-mail ID | ✓ |
| 8 | Passport-size photograph | ✓ |
| 9 | Authority Letter, if application filed through representative | If applicable |
| 10 | Affidavit/undertaking regarding correctness of information | Recommended |
B. If Applicant is a Company / Pvt. Ltd. Company
For a company such as ARC Cold Store Installations Private Limited, keep:
- Certificate of Incorporation
- PAN of Company
- Memorandum of Association
- Articles of Association
- Board Resolution authorising CLU application
- Authorisation letter in favour of authorised signatory
- PAN/Aadhaar of authorised signatory
- Registered office address proof
- GST Registration, if available
- Company profile
- Project report / DPR
The CLU checklist used in J&K also specifically identifies MOA/AOA, Board Resolution and authority letter for company applicants.
2. LAND OWNERSHIP DOCUMENTS
This is one of the most important sections of the CLU file.
| S. No. | Document | Remarks |
|---|---|---|
| 1 | Latest Jamabandi / Record of Rights | Certified/latest copy |
| 2 | Latest Khasra Girdawari | Should reflect present land use |
| 3 | Mutation / Intqal | Latest ownership mutation |
| 4 | Sale Deed / Title Deed | Registered document |
| 5 | Takseem Intqal | Where applicable |
| 6 | Aks Shajra | Certified revenue map |
| 7 | Tatima | Where part of a Khasra is involved |
| 8 | Land Passbook | Where available |
| 9 | Encumbrance details | Recommended |
| 10 | Court case/litigation status | Declaration, where applicable |
| 11 | Co-owner consent | If jointly owned |
| 12 | Irrevocable consent/authority from owner | If applicant is not the recorded owner |
The official 2022 regulations specifically require revenue extracts including Jamabandi and Khasra Girdawari, together with the sale deed and location plan. The prescribed application material also refers to mutation, Jamabandi, Aks/Tatima and Khasra Girdawari.
3. SITE & LOCATION DOCUMENTS
Prepare a separate Site & Location File containing:
3.1 Key Location Plan
The plan should clearly show:
- District
- Tehsil
- Village
- Khasra number
- Approach road
- Nearby road/highway
- North direction
- Nearby habitation
- Nearby water bodies, if any
- Existing buildings
- Existing land use
- Proposed project location
3.2 Revenue Site Plan
Attach:
- Aks Shajra
- Tatima, where required
- Khasra boundaries
- Total land area
- Area proposed for CLU
- Remaining agricultural area, if applicable
3.3 Proposed Layout Plan
For a cold-storage/industrial project, show:
- Main building
- Cold chambers
- PEB structure
- Refrigeration plant room
- Loading/unloading area
- Office
- Parking
- Internal roads
- Generator room
- Transformer/electrical room
- Fire-fighting facilities
- Water storage
- STP/ETP, if applicable
- Drainage
- Greenbelt
- Boundary wall
- Entry/exit gate
4. MASTER PLAN / LAND-USE STATUS
This is very important in Kashmir.
Obtain a report/confirmation regarding:
“Land Use as per Master Plan / Development Plan”
from the concerned Town Planning / Development Authority / DTP office, as applicable.
The application should clearly establish:
Existing Land Use: Agricultural
Proposed Land Use: Industrial / Commercial / Institutional / Hospitality / Warehouse / Cold Storage, etc.
The CLU process specifically involves examination of whether the proposed use conforms to the applicable Master Plan/Development Plan.
5. PROJECT DOCUMENTS
For a commercial/industrial CLU application, I recommend attaching a concise Project Report/DPR containing:
Project Profile
- Name of project
- Name of promoter/company
- Location
- Village
- Tehsil
- District
- Khasra number
- Total land area
- Area proposed for CLU
- Existing land use
- Proposed land use
- Nature of business
- Project capacity
- Project cost
- Machinery/equipment
- Employment generation
- Power requirement
- Water requirement
- Wastewater generation
- Solid waste generation
- Pollution-control arrangements
- Parking/loading arrangements
- Fire-safety arrangements
- Proposed construction area
- Building height
- Green area
- Expected commencement date
6. NOC / DEPARTMENTAL CLEARANCE CHECKLIST
The exact NOCs depend on the location and proposed activity. The 2022 CLU procedure provides for circulation to relevant departments including PWD, Irrigation & Flood Control, Power Development, Pollution Control Committee, Agriculture, Industries & Commerce, Development Authority and Forests, as applicable.
A. Revenue Department
Revenue field verification
Normally covers:
- Ownership
- Khasra
- Area
- Land classification
- Existing use
- Encumbrances
- Revenue record verification
- Site verification
B. Town Planning / Development Authority
Obtain, where applicable:
Master Plan / Development Plan conformity report
and/or:
Land-use compatibility/NOC
This is particularly important if the property falls within:
- Srinagar Master Plan
- Development Authority jurisdiction
- Municipal limits
- Local Planning Area
- Notified development area
C. Agriculture Department
Particularly relevant where the land is recorded as agricultural.
The department may examine:
- Nature of agricultural land
- Existing cultivation
- Agricultural importance
- Proposed diversion
- Impact on agricultural land
D. Industries & Commerce Department
For projects such as:
- Cold storage
- Food processing
- Manufacturing
- Industrial units
- Warehouses
- Packaging units
an appropriate industrial/project-related approval or recommendation may be required depending upon the project.
E. Pollution Control Committee (PCC)
For projects having environmental implications, obtain the applicable:
- Consent to Establish
- Consent to Operate, at the appropriate stage
- Environmental clearance, if applicable
- Waste-management permissions, if applicable
For a conventional cold store, the exact PCC requirement should be determined based on the proposed refrigeration system, DG set, wastewater, processing activity and applicable pollution-control category.
F. PWD / Roads & Buildings
Relevant where the project:
- abuts a government road,
- requires an approach/access,
- involves road widening restrictions, or
- falls within a controlled road corridor.
Obtain road/access NOC where applicable.
G. Jal Shakti Department
Relevant where the project requires:
- substantial water supply,
- connection to a public water system,
- groundwater/borewell permissions,
- water-resource infrastructure.
H. Irrigation & Flood Control Department
Important particularly for land:
- near canals,
- near irrigation channels,
- near flood channels,
- near rivers/nallahs,
- in flood-prone areas.
The department is expressly included in the district-level CLU review mechanism.
I. Power Development / KPDCL
For industrial/commercial projects, obtain applicable power feasibility/NOC, particularly where substantial sanctioned load is required.
For a cold store, mention:
- Connected load
- Contract demand
- Transformer requirement
- DG backup
- Solar installation, if proposed
J. Forest Department
Required where the land:
- is adjacent to forest land,
- falls within/near notified forest areas,
- involves forest clearance issues,
- has trees requiring permission for removal.
K. Wildlife Department
Particularly important if the property is:
- near a wildlife sanctuary,
- near a national park,
- within an eco-sensitive zone,
- near a protected area.
L. National Highways Authority / Highway Authority
Where applicable, obtain NOC for:
- National Highway access
- Highway frontage
- Entry/exit
- Setback/control zone
The 2022 procedure specifically contemplates reference to the highway authority where required.
7. SPECIAL NOC CHECKLIST FOR A COLD STORAGE
Since your current work frequently involves cold-storage/CA-store projects, I would prepare the CLU file as follows:
Mandatory/Core File
☐ CLU Application
☐ Jamabandi
☐ Khasra Girdawari
☐ Mutation
☐ Sale Deed
☐ Aks Shajra
☐ Tatima, if applicable
☐ Key Location Plan
☐ Site Plan
☐ Proposed Layout
☐ Master Plan/Development Plan status
☐ Project Report/DPR
☐ Company documents
☐ Board Resolution
☐ Authorisation Letter
Project-Specific NOCs
☐ Agriculture Department
☐ Town Planning/DTP/Development Authority
☐ Industries & Commerce
☐ PCC
☐ PWD/R&B
☐ Jal Shakti
☐ Irrigation & Flood Control
☐ KPDCL/PDD
☐ Forest, if applicable
☐ Wildlife, if applicable
☐ Highway Authority, if applicable
☐ Fire & Emergency Services, at the building/project approval stage
☐ Any other department identified by the District Level Committee
The District Level Committee includes the DC as Chairman and ACR as Member Secretary, with senior officers from departments such as PWD, Irrigation & Flood Control, Power, PCC where required, Agriculture, Industries & Commerce, Development Authority and Forests.
8. READY-TO-USE CLU APPLICATION FORMAT
To
The District Collector / Deputy Commissioner
District ____________
Union Territory of Jammu & Kashmir
Subject: Application for Permission for Change/Conversion of Land Use from Agricultural to Non-Agricultural Purpose under Section 133-A of the J&K Land Revenue Act, Svt. 1996 and the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022
Sir/Madam,
I/We, ____________________________, S/o / D/o / W/o ____________________________, resident of ____________________________, hereby submit this application seeking permission for conversion/change of land use of the agricultural land detailed below for the purpose of ____________________________.
1. PARTICULARS OF APPLICANT
| Particular | Details |
|---|---|
| Name of Applicant/Company | __________________________ |
| Father’s/Husband’s Name | __________________________ |
| Constitution | Individual / Partnership / Pvt. Ltd. / Ltd. / Other |
| Permanent Address | __________________________ |
| Correspondence Address | __________________________ |
| Mobile No. | __________________________ |
| __________________________ | |
| PAN | __________________________ |
| Aadhaar/ID | __________________________ |
2. PARTICULARS OF LAND
| Particular | Details |
|---|---|
| District | __________________ |
| Tehsil | __________________ |
| Village | __________________ |
| Patwar Halqa | __________________ |
| Khewat No. | __________________ |
| Khata No. | __________________ |
| Khasra No. | __________________ |
| Total Area | __________________ |
| Area Proposed for CLU | __________________ |
| Present Land Use | Agricultural |
| Proposed Land Use | __________________ |
| Mode of Ownership | Sale / Inheritance / Gift / Other |
| Sale Deed/Mutation No. | __________________ |
3. PURPOSE OF CHANGE OF LAND USE
The proposed land is intended to be utilized for:
________________________________________________________
The proposed development shall comprise:
4. PROJECT PARTICULARS
Name of Project: ______________________________
Project Cost: Rs. ______________________________
Proposed Built-up Area: __________________ Sft.
Employment Generation: __________________ persons
Power Requirement: __________________ KW/KVA
Water Requirement: __________________ KLD
Nature of Activity: ______________________________
5. DECLARATION
I/We hereby declare that the information furnished in this application and the documents attached herewith are true and correct to the best of my/our knowledge and belief.
I/We undertake that the land shall be utilized only for the purpose for which permission is granted and that all applicable laws, rules, Master Plan provisions, environmental requirements and departmental approvals shall be complied with.
I/We further undertake to deposit the prescribed conversion fee/charges as demanded by the competent authority and to comply with all conditions imposed in the permission order.
I/We understand that any misrepresentation or use of the land for a purpose other than the approved purpose may attract action under the applicable laws.
Date: ____________
Place: ____________
Signature: ______________________
Name: _________________________
Designation: ____________________
Mobile: ________________________
Seal of Company, if applicable
LIST OF ENCLOSURES
- CLU Application Form
- Latest Jamabandi
- Latest Khasra Girdawari
- Mutation/Intqal
- Sale Deed/Title Document
- Aks Shajra
- Tatima/Takseem Intqal, wherever applicable
- Key Location Plan
- Site Plan
- Proposed Layout Plan
- Master Plan/Development Plan status/report
- Project Report/DPR
- Company Incorporation Certificate, if applicable
- MOA & AOA, if applicable
- Board Resolution, if applicable
- Authority Letter
- PAN/Aadhaar/Identity Documents
- Applicable Departmental NOCs
- Other supporting documents as required by the competent authority.
9. CLU PROCESS — PRACTICAL FLOW
Step 1 — Verify Land Records
↓
Jamabandi + Girdawari + Mutation + Aks Shajra + Sale Deed
Step 2 — Verify Proposed Land Use
↓
Master Plan / Development Plan / DTP
Step 3 — Prepare Project File
↓
DPR + Site Plan + Layout + Investment + Capacity
Step 4 — File CLU Application
↓
District Collector’s designated web portal/process
Step 5 — Revenue Verification
↓
Tehsildar / Revenue Field Staff
Step 6 — Departmental NOCs/Reports
↓
PWD + Jal Shakti + Irrigation + Power + Agriculture + Industries + PCC + Forest/others as applicable
Step 7 — District Level Committee
↓
DC/Collector + ACR + concerned departments
Step 8 — Recommendation
↓
Step 9 — Demand Notice for Conversion Fee
↓
Step 10 — Deposit Conversion Fee
↓
Step 11 — Submit Treasury Challan
↓
Step 12 — CLU Permission Order
↓
Step 13 — Mutation/Revenue Record Updating, as applicable
↓
Step 14 — Building/Development Permission
The regulations provide that, after recommendation, the District Collector issues a demand notice for the conversion fee, with the applicant required to submit the Treasury Challan within the prescribed period. The permission is subject to conditions, including use only for the approved purpose and commencement of the approved non-agricultural use within the prescribed period.
Important distinction
CLU permission is not the same as building permission.
After obtaining CLU, the promoter may still need separate approvals for building plan, fire safety, pollution control, electricity, water, highway access, environmental requirements and other project-specific permissions.
Also, if the proposed use is already permissible under the applicable Master Plan/Development Plan, Section 133-A provides a separate route involving payment of prescribed conversion charges.
For ARC Cold Store / CA Store Projects
For a cold storage/CA store on agricultural land in Kashmir, I would recommend preparing the file as a three-part submission:
PART-I — CLU LEGAL/REVENUE FILE
Land ownership + revenue records + CLU application.
PART-II — LAND-USE & NOC FILE
Master Plan + DTP + Agriculture + PWD + Irrigation + Power + PCC + Forest/Wildlife/Highway, as applicable.
PART-III — PROJECT/DPR FILE
Cold-store capacity + chambers + refrigeration + PEB + civil works + investment + employment + water/power requirements + waste management + site layout.
This gives the District Level Committee a much clearer basis for considering the proposal.