Change of Land Use (CLU) in Kashmir/Jammu & Kashmir, particularly conversion of agricultural land to non-agricultural use such as commercial, industrial, hotel, cold storage, warehouse, etc., the application is generally dealt with under Section 133-A of the J&K Land Revenue Act, 1996 and the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022. The competent authority is the District Collector (Deputy Commissioner).

Below is a practical, Kashmir-specific CLU file checklist, NOC checklist and ready-to-use application format for conversion of agricultural land to non-agricultural use.

The current framework is the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022, issued under the J&K Land Revenue Act. The District Collector/DC is the competent authority, and applications are processed through the district-level mechanism. The regulations provide for online filing and ordinarily contemplate disposal within 30 days once the application is complete.

1. MASTER CLU DOCUMENT CHECKLIST — KASHMIR

A. Application & Applicant Documents

S. No.DocumentRequired
1Prescribed CLU Application Form✓
2Applicant’s full name✓
3Parentage / constitution of applicant✓
4Permanent & correspondence address✓
5Aadhaar / valid identity proof✓
6PAN Card✓
7Mobile No. & E-mail ID✓
8Passport-size photograph✓
9Authority Letter, if application filed through representativeIf applicable
10Affidavit/undertaking regarding correctness of informationRecommended

B. If Applicant is a Company / Pvt. Ltd. Company

For a company such as ARC Cold Store Installations Private Limited, keep:

  1. Certificate of Incorporation
  2. PAN of Company
  3. Memorandum of Association
  4. Articles of Association
  5. Board Resolution authorising CLU application
  6. Authorisation letter in favour of authorised signatory
  7. PAN/Aadhaar of authorised signatory
  8. Registered office address proof
  9. GST Registration, if available
  10. Company profile
  11. Project report / DPR

The CLU checklist used in J&K also specifically identifies MOA/AOA, Board Resolution and authority letter for company applicants.


2. LAND OWNERSHIP DOCUMENTS

This is one of the most important sections of the CLU file.

S. No.DocumentRemarks
1Latest Jamabandi / Record of RightsCertified/latest copy
2Latest Khasra GirdawariShould reflect present land use
3Mutation / IntqalLatest ownership mutation
4Sale Deed / Title DeedRegistered document
5Takseem IntqalWhere applicable
6Aks ShajraCertified revenue map
7TatimaWhere part of a Khasra is involved
8Land PassbookWhere available
9Encumbrance detailsRecommended
10Court case/litigation statusDeclaration, where applicable
11Co-owner consentIf jointly owned
12Irrevocable consent/authority from ownerIf applicant is not the recorded owner

The official 2022 regulations specifically require revenue extracts including Jamabandi and Khasra Girdawari, together with the sale deed and location plan. The prescribed application material also refers to mutation, Jamabandi, Aks/Tatima and Khasra Girdawari.


3. SITE & LOCATION DOCUMENTS

Prepare a separate Site & Location File containing:

3.1 Key Location Plan

The plan should clearly show:

  • District
  • Tehsil
  • Village
  • Khasra number
  • Approach road
  • Nearby road/highway
  • North direction
  • Nearby habitation
  • Nearby water bodies, if any
  • Existing buildings
  • Existing land use
  • Proposed project location

3.2 Revenue Site Plan

Attach:

  • Aks Shajra
  • Tatima, where required
  • Khasra boundaries
  • Total land area
  • Area proposed for CLU
  • Remaining agricultural area, if applicable

3.3 Proposed Layout Plan

For a cold-storage/industrial project, show:

  • Main building
  • Cold chambers
  • PEB structure
  • Refrigeration plant room
  • Loading/unloading area
  • Office
  • Parking
  • Internal roads
  • Generator room
  • Transformer/electrical room
  • Fire-fighting facilities
  • Water storage
  • STP/ETP, if applicable
  • Drainage
  • Greenbelt
  • Boundary wall
  • Entry/exit gate

4. MASTER PLAN / LAND-USE STATUS

This is very important in Kashmir.

Obtain a report/confirmation regarding:

“Land Use as per Master Plan / Development Plan”

from the concerned Town Planning / Development Authority / DTP office, as applicable.

The application should clearly establish:

Existing Land Use: Agricultural
Proposed Land Use: Industrial / Commercial / Institutional / Hospitality / Warehouse / Cold Storage, etc.

The CLU process specifically involves examination of whether the proposed use conforms to the applicable Master Plan/Development Plan.


5. PROJECT DOCUMENTS

For a commercial/industrial CLU application, I recommend attaching a concise Project Report/DPR containing:

Project Profile

  1. Name of project
  2. Name of promoter/company
  3. Location
  4. Village
  5. Tehsil
  6. District
  7. Khasra number
  8. Total land area
  9. Area proposed for CLU
  10. Existing land use
  11. Proposed land use
  12. Nature of business
  13. Project capacity
  14. Project cost
  15. Machinery/equipment
  16. Employment generation
  17. Power requirement
  18. Water requirement
  19. Wastewater generation
  20. Solid waste generation
  21. Pollution-control arrangements
  22. Parking/loading arrangements
  23. Fire-safety arrangements
  24. Proposed construction area
  25. Building height
  26. Green area
  27. Expected commencement date

6. NOC / DEPARTMENTAL CLEARANCE CHECKLIST

The exact NOCs depend on the location and proposed activity. The 2022 CLU procedure provides for circulation to relevant departments including PWD, Irrigation & Flood Control, Power Development, Pollution Control Committee, Agriculture, Industries & Commerce, Development Authority and Forests, as applicable.

A. Revenue Department

Revenue field verification

Normally covers:

  • Ownership
  • Khasra
  • Area
  • Land classification
  • Existing use
  • Encumbrances
  • Revenue record verification
  • Site verification

B. Town Planning / Development Authority

Obtain, where applicable:

Master Plan / Development Plan conformity report

and/or:

Land-use compatibility/NOC

This is particularly important if the property falls within:

  • Srinagar Master Plan
  • Development Authority jurisdiction
  • Municipal limits
  • Local Planning Area
  • Notified development area

C. Agriculture Department

Particularly relevant where the land is recorded as agricultural.

The department may examine:

  • Nature of agricultural land
  • Existing cultivation
  • Agricultural importance
  • Proposed diversion
  • Impact on agricultural land

D. Industries & Commerce Department

For projects such as:

  • Cold storage
  • Food processing
  • Manufacturing
  • Industrial units
  • Warehouses
  • Packaging units

an appropriate industrial/project-related approval or recommendation may be required depending upon the project.


E. Pollution Control Committee (PCC)

For projects having environmental implications, obtain the applicable:

  • Consent to Establish
  • Consent to Operate, at the appropriate stage
  • Environmental clearance, if applicable
  • Waste-management permissions, if applicable

For a conventional cold store, the exact PCC requirement should be determined based on the proposed refrigeration system, DG set, wastewater, processing activity and applicable pollution-control category.


F. PWD / Roads & Buildings

Relevant where the project:

  • abuts a government road,
  • requires an approach/access,
  • involves road widening restrictions, or
  • falls within a controlled road corridor.

Obtain road/access NOC where applicable.


G. Jal Shakti Department

Relevant where the project requires:

  • substantial water supply,
  • connection to a public water system,
  • groundwater/borewell permissions,
  • water-resource infrastructure.

H. Irrigation & Flood Control Department

Important particularly for land:

  • near canals,
  • near irrigation channels,
  • near flood channels,
  • near rivers/nallahs,
  • in flood-prone areas.

The department is expressly included in the district-level CLU review mechanism.


I. Power Development / KPDCL

For industrial/commercial projects, obtain applicable power feasibility/NOC, particularly where substantial sanctioned load is required.

For a cold store, mention:

  • Connected load
  • Contract demand
  • Transformer requirement
  • DG backup
  • Solar installation, if proposed

J. Forest Department

Required where the land:

  • is adjacent to forest land,
  • falls within/near notified forest areas,
  • involves forest clearance issues,
  • has trees requiring permission for removal.

K. Wildlife Department

Particularly important if the property is:

  • near a wildlife sanctuary,
  • near a national park,
  • within an eco-sensitive zone,
  • near a protected area.

L. National Highways Authority / Highway Authority

Where applicable, obtain NOC for:

  • National Highway access
  • Highway frontage
  • Entry/exit
  • Setback/control zone

The 2022 procedure specifically contemplates reference to the highway authority where required.


7. SPECIAL NOC CHECKLIST FOR A COLD STORAGE

Since your current work frequently involves cold-storage/CA-store projects, I would prepare the CLU file as follows:

Mandatory/Core File

☐ CLU Application
☐ Jamabandi
☐ Khasra Girdawari
☐ Mutation
☐ Sale Deed
☐ Aks Shajra
☐ Tatima, if applicable
☐ Key Location Plan
☐ Site Plan
☐ Proposed Layout
☐ Master Plan/Development Plan status
☐ Project Report/DPR
☐ Company documents
☐ Board Resolution
☐ Authorisation Letter

Project-Specific NOCs

☐ Agriculture Department
☐ Town Planning/DTP/Development Authority
☐ Industries & Commerce
☐ PCC
☐ PWD/R&B
☐ Jal Shakti
☐ Irrigation & Flood Control
☐ KPDCL/PDD
☐ Forest, if applicable
☐ Wildlife, if applicable
☐ Highway Authority, if applicable
☐ Fire & Emergency Services, at the building/project approval stage
☐ Any other department identified by the District Level Committee

The District Level Committee includes the DC as Chairman and ACR as Member Secretary, with senior officers from departments such as PWD, Irrigation & Flood Control, Power, PCC where required, Agriculture, Industries & Commerce, Development Authority and Forests.


8. READY-TO-USE CLU APPLICATION FORMAT

To
The District Collector / Deputy Commissioner
District ____________
Union Territory of Jammu & Kashmir

Subject: Application for Permission for Change/Conversion of Land Use from Agricultural to Non-Agricultural Purpose under Section 133-A of the J&K Land Revenue Act, Svt. 1996 and the J&K Agricultural Land (Conversion for Non-Agricultural Purposes) Regulations, 2022

Sir/Madam,

I/We, ____________________________, S/o / D/o / W/o ____________________________, resident of ____________________________, hereby submit this application seeking permission for conversion/change of land use of the agricultural land detailed below for the purpose of ____________________________.

1. PARTICULARS OF APPLICANT

ParticularDetails
Name of Applicant/Company__________________________
Father’s/Husband’s Name__________________________
ConstitutionIndividual / Partnership / Pvt. Ltd. / Ltd. / Other
Permanent Address__________________________
Correspondence Address__________________________
Mobile No.__________________________
E-mail__________________________
PAN__________________________
Aadhaar/ID__________________________

2. PARTICULARS OF LAND

ParticularDetails
District__________________
Tehsil__________________
Village__________________
Patwar Halqa__________________
Khewat No.__________________
Khata No.__________________
Khasra No.__________________
Total Area__________________
Area Proposed for CLU__________________
Present Land UseAgricultural
Proposed Land Use__________________
Mode of OwnershipSale / Inheritance / Gift / Other
Sale Deed/Mutation No.__________________

3. PURPOSE OF CHANGE OF LAND USE

The proposed land is intended to be utilized for:

________________________________________________________

The proposed development shall comprise:

4. PROJECT PARTICULARS

Name of Project: ______________________________

Project Cost: Rs. ______________________________

Proposed Built-up Area: __________________ Sft.

Employment Generation: __________________ persons

Power Requirement: __________________ KW/KVA

Water Requirement: __________________ KLD

Nature of Activity: ______________________________

5. DECLARATION

I/We hereby declare that the information furnished in this application and the documents attached herewith are true and correct to the best of my/our knowledge and belief.

I/We undertake that the land shall be utilized only for the purpose for which permission is granted and that all applicable laws, rules, Master Plan provisions, environmental requirements and departmental approvals shall be complied with.

I/We further undertake to deposit the prescribed conversion fee/charges as demanded by the competent authority and to comply with all conditions imposed in the permission order.

I/We understand that any misrepresentation or use of the land for a purpose other than the approved purpose may attract action under the applicable laws.

Date: ____________

Place: ____________

Signature: ______________________

Name: _________________________

Designation: ____________________

Mobile: ________________________

Seal of Company, if applicable

LIST OF ENCLOSURES

  1. CLU Application Form
  2. Latest Jamabandi
  3. Latest Khasra Girdawari
  4. Mutation/Intqal
  5. Sale Deed/Title Document
  6. Aks Shajra
  7. Tatima/Takseem Intqal, wherever applicable
  8. Key Location Plan
  9. Site Plan
  10. Proposed Layout Plan
  11. Master Plan/Development Plan status/report
  12. Project Report/DPR
  13. Company Incorporation Certificate, if applicable
  14. MOA & AOA, if applicable
  15. Board Resolution, if applicable
  16. Authority Letter
  17. PAN/Aadhaar/Identity Documents
  18. Applicable Departmental NOCs
  19. Other supporting documents as required by the competent authority.

9. CLU PROCESS — PRACTICAL FLOW

Step 1 — Verify Land Records
↓
Jamabandi + Girdawari + Mutation + Aks Shajra + Sale Deed

Step 2 — Verify Proposed Land Use
↓
Master Plan / Development Plan / DTP

Step 3 — Prepare Project File
↓
DPR + Site Plan + Layout + Investment + Capacity

Step 4 — File CLU Application
↓
District Collector’s designated web portal/process

Step 5 — Revenue Verification
↓
Tehsildar / Revenue Field Staff

Step 6 — Departmental NOCs/Reports
↓
PWD + Jal Shakti + Irrigation + Power + Agriculture + Industries + PCC + Forest/others as applicable

Step 7 — District Level Committee
↓
DC/Collector + ACR + concerned departments

Step 8 — Recommendation

↓

Step 9 — Demand Notice for Conversion Fee

↓

Step 10 — Deposit Conversion Fee

↓

Step 11 — Submit Treasury Challan

↓

Step 12 — CLU Permission Order

↓

Step 13 — Mutation/Revenue Record Updating, as applicable

↓

Step 14 — Building/Development Permission

The regulations provide that, after recommendation, the District Collector issues a demand notice for the conversion fee, with the applicant required to submit the Treasury Challan within the prescribed period. The permission is subject to conditions, including use only for the approved purpose and commencement of the approved non-agricultural use within the prescribed period.

Important distinction

CLU permission is not the same as building permission.

After obtaining CLU, the promoter may still need separate approvals for building plan, fire safety, pollution control, electricity, water, highway access, environmental requirements and other project-specific permissions.

Also, if the proposed use is already permissible under the applicable Master Plan/Development Plan, Section 133-A provides a separate route involving payment of prescribed conversion charges.

For ARC Cold Store / CA Store Projects

For a cold storage/CA store on agricultural land in Kashmir, I would recommend preparing the file as a three-part submission:

PART-I — CLU LEGAL/REVENUE FILE
Land ownership + revenue records + CLU application.

PART-II — LAND-USE & NOC FILE
Master Plan + DTP + Agriculture + PWD + Irrigation + Power + PCC + Forest/Wildlife/Highway, as applicable.

PART-III — PROJECT/DPR FILE
Cold-store capacity + chambers + refrigeration + PEB + civil works + investment + employment + water/power requirements + waste management + site layout.

This gives the District Level Committee a much clearer basis for considering the proposal.